Secondary Aluminum Production

Air Toxics Notebook

Secondary Aluminum Production

Applicability

eCFR Subpart RRR [ecfr.gov]

This subpart applies to:

  1. Affected sources at secondary aluminum production facilities that are Major or Area Sources of HAPs*.

Affected sources:

  1. At Major Sources:
    1. Aluminum scrap shredders;
    2. Thermal chip dryers;
    3. Scrap dryers, delacquering kilns, and decoating kilns;
    4. Group 2 furnaces;
    5. Sweat furnaces;
    6. Dross-only furnaces;
    7. Rotary dross coolers;
    8. Secondary aluminum processing units.
  2. At Area Sources:
    1. Thermal chip dryers;
    2. Scrap dryers, delacquering kilns, and decoating kilns;
    3. Sweat furnaces;
    4. Secondary aluminum processing units containing one or more group 1 furnace emission units other than clean charge.


Not subject to this subpart:

  1. Research and development facilities that are not used to produce a saleable product.


*Major Sources of HAPs emit or have the potential to emit:

  • ≥ 10 tons/year of any single HAP; or
  • ≥ 25 tons/year of total HAPs.
  • Area Sources emit less than Major Sources.
Rules apply to small, area sources?
Yes
Known Sources in NDEE Jurisdiction
Facility IDNameLocation
55408Andersen Wrecking CoKearney
Date of Original Final Rule
Amendments Dates

06/13/2016 - Direct Final Rule
09/18/2015 - Final Rule
04/20/2006 - Amendments
12/19/2005 - Final Rule
10/03/2005 - Amendments
09/03/2004 - Amendments
06/23/2003 - Amendments
12/30/2002 - Amendments
09/24/2002 - Amendments
06/14/2002 - Amendments

State Regulations

Title 129, Chapter 13, Section 002.51

Previously: Chapter 28, Section 001.49.

Sources are also responsible for ensuring they are in compliance with current federal requirements found for this subpart in the CFR

Federal Regulations
40 CFR 63.1500
Related Rules

NSPS - 40 CFR Part 60

Subpart S - Primary Aluminum Production

 

NESHAP - 40 CFR Part 63

Subpart LL - Primary Aluminum Reduction
Subpart TTTTTT - Secondary Non-ferrous Metals Processing
Subpart ZZZZZZ - Aluminum, Copper, and Non-ferrous foundries

Important Dates

Source Classification

  • Existing Source = commenced construction or reconstruction on or before Feb 11, 1999.
  • New Source = commenced construction or reconstruction after Feb 11, 1999.

Initial Notification

  • Existing Source = Must submit by Jul 22, 2003.
  • New Source = Must submit by Jul 22, 2000 or within 120 days of initial startup, whichever is later.

Compliance Date

  • Existing Source = Mar 24, 2003.
  • New Source = Mar 24, 2000 or upon startup, whichever is later.

Notification of Compliance Status

  • Existing Source = Must submit by May 23, 2003.
  • New Source = Must submit within 90 days of compliance date (or within 90 days of any initial performance test, if required).
Other Information and Resources

EPA's Subpart RRR Website [epa.gov] - contains federal register notices, compliance workbooks, sample plans and reports, compliance timeline, inspector checklist, and more

Page Last Updated