Electric Arc Furnace Steelmaking Facilities
Air Toxics Notebook
Electric Arc Furnace Steelmaking Facilities
eCFR Subpart YYYYY [ecfr.gov]
This subpart applies to owners and operators of new and existing electric arc furnace (EAF) steelmaking facilities that are area sources of hazardous air pollutants. For the purposes of this subpart an EAF steelmaking facility means a steel plant that produces carbon, alloy, or specialty steels using an EAF.
This subpart does not apply to the following:
- Research and development facilities.
- EAF steelmaking facilities at steel foundries.
- EAF steelmaking facilities used to produce nonferrous metals.
*An area source of HAP has the potential to emit <10 tons per year (tpy) of a single HAP or <25 tpy of a combination of HAPs.
Facility ID | Name | Location |
35677 | Nucor Steel | Norfolk |
2/26/2009 - Withdrawal of Direct Final Rule Amendments of 12/1/08
12/01/2008 - Direct Final Rule Amendments
Title 129, Chapter 13, Section 002.92
Previously: Chapter 28, Section 001.103.
Sources are also responsible for ensuring they are in compliance with current federal requirements found for this subpart in the CFR.
NSPS - 40 CFR Part 60
Subpart AA & AAa - Electric Arc Furnaces
Subpart N & Na - Primary & Secondary Emissions from Basic Oxygen Process
NESHAP - 40 CFR Part 63
Subpart CCC - Steel Pickling
Subpart EEEEE - Iron & Steel Foundries
Subpart FFFFF - Integrated Iron & Steel
Subpart ZZZZZ - Iron & Steel Foundries (area sources)
eCFR Subpart YYYYY [ecfr.gov]
231 KB | 5Y - Fed. Reg. 12-28- 2007 - final rule.pdf |
Source Classification
- Existing Source = constructed or reconstructed on or before 9/20/2007
- New Source = constructed or reconstructed after 9/20/2007
Compliance Dates
- Existing source = 6/30/2008
- New source = 12/28/2007 or upon startup
Initial Notification
- Existing source = 4/26/2008
- New source = 120 days after startup
Notice of Intent to Test
- 60 days prior to test
Compliance Status Notification
- Existing source = 7/30/2008 or 60 days after test (if required)
- New source = 30 days after compliance date or 60 days after test (if required)
Compliance Report
- Semiannual
- According to schedule in Title V operating permit
105 KB | 5Y - EPA Brochure.pdf |
EPA's Subpart YYYYY Website [epa.gov] - contains federal register notices and implementation tools.