Skip to main content

Stationary Gas Turbines - Subpart GG

NSPS Notebook

Stationary Gas Turbines - Subpart GG

Applicability

eCFR Subpart GG [ecfr.gov]

This subpart applies to:

  1. Stationary gas turbines that meet both of the following conditions:
    1. Heat input at peak load of ≥ 10.7 gigajoules (10 MMBtu) per hour, based on the lower heating value of the fuel;
    2. Commenced construction, modification, or reconstruction after Oct 3, 1977.

Stationary gas turbines which commenced construction, modification, or reconstruction after February 18, 2005 are subject to NSPS KKKK.

Date of Original Final Rule
Amendments Dates

08/29/2012 - Proposed Rule
02/24/2006 - Direct Final Rule
07/08/2004 - FInal Rule; Amendments
05/28/2003 - Withdrawal of Direct Final Rule
04/14/2003 - Direct Final Rule
11/05/1987 - Final Rule; Correction
01/27/1982 - Final Rule
09/10/1979 - Final Rule

State Regulations

Title 129, Chapter 12, Section 001.38

Previously: Chapter 18, Section 001.53.

Sources are also responsible for ensuring they are in compliance with current federal requirements found for this subpart in the CFR.

Federal Regulations
40 CFR 60.330
Related Rules

NSPS - 40 CFR Part 60

Subpart KKKK - Combustion turbines
Subparts Da, Db, and Dc - Steam-generating units

 

NESHAP - 40 CFR Part 63

Subpart YYYY - Stationary combustion turbines

Regulations and Federal Registers

eCFR Subpart GG [ecfr.gov]

FAQ's, Fact Sheets, and Rules Summaries

EPA's NSPS Turbine Website [epa.gov] - contains federal register notices and technical information

EPA Sponsored Combustion Portal [combustionportal.org] - Federal & state compliance information & sustainability content for combustion processes

Page Last Updated